This section is the ④ high-throughput principle worked out. The design is pull-based and leaderless: there is no broker and no coordinator process — workers pull work from the state store, and the store's atomic primitives are the only coordination. Because those primitives are backend-neutral (the same claim/lease contract over SQLite / Firestore / DynamoDB), throughput is ② provider-agnostic too.

The unit is the only granularity

A run is planned into work units — contiguous document index ranges. The unit is simultaneously the granularity of claiming, sharding (one golden shard per unit per table), the manifest part, and the export read. Size it (unit_size) so there are comfortably more units than tasks — ideally 2–3× — or some tasks finish with nothing to do.

Two levels of concurrency

flowchart TB
    subgraph Pool["one run = one unit pool (state store)"]
        U1["unit"]:::u
        U2["unit"]:::u
        U3["unit"]:::u
        U4["unit"]:::u
    end
    T1["task 1"] -->|atomic claim| Pool
    T2["task 2"] -->|atomic claim| Pool
    T3["task N"] -->|atomic claim| Pool
    classDef u fill:#eee,stroke:#999;
  • Across tasks — N Cloud Run tasks run the same drain loop against one pool; the atomic claim guarantees no unit is worked twice.
  • Within a task — a catalogue build makes async LLM calls concurrently (bounded by --concurrency); document rendering is sequential per task (Chromium), so within-task parallelism is the LLM path, not the render path.

The coordination contract

  • Atomic claim. Advance this unit to RUNNING only if still PENDING — one conditional write per backend (SQLite BEGIN IMMEDIATE, Firestore transaction, DynamoDB ConditionExpression). A lost race just moves to the next candidate.
  • Lease + reclaim. A claim stamps a lease; an expired lease is reclaimable, so a crashed worker's unit returns to the pool. SQLite reclaims opportunistically inside the claim (a draining fleet self-heals with no resume); Firestore / DynamoDB reclaim explicitly (reclaim_expired_units) on resume and at the start of a catalogue build — a per-claim scan would be too costly at scale.
  • Planning race. The run marker and its units are not one write, so Run.planned gates claiming: a worker that loses the conditional create_run either waits for the peer's plan to land or — if already planned (a re-run / retried task) — logs "already planned; resuming" and proceeds. This is what makes cold-starting N tasks safe.
  • Completion contract. The root manifest's presence = done. It refuses to write over a gap, and a partial run leaves parts but no root, so a consumer never reads an incomplete run as complete. A worker exits non-zero only for real holes (failed units), never because peers are still finishing.

Fleet budget

An LLM catalogue build under a fleet must not let N tasks each spend up to the cap. DistributedBudgetGuard counts against the run's spend rollup in the state store, so the budget holds across workers, not per process.

The work-unit lifecycle and the per-backend claim internals are on the State stores page; the end-to-end sequences are in Execution flows.